Topic 1, Volume A
Which document defines how a project is executed, monitored and controlled, and closed?
A.
Strategic plan
B.
Project charter
C.
Project management plan
D.
Service level agreement
Project management plan
Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a
typical project progresses?
A.
Risk and uncertainty increase; the cost of changes increases.
B.
Risk and uncertainty increase; the cost of changes decreases,
C.
Risk and uncertainty decrease; the cost of changes increases.
D.
Risk and uncertainty decrease; the cost of changes decreases.
Risk and uncertainty decrease; the cost of changes increases.
Which tool or technique is used in the Plan Scope Management process?
A.
Document analysis
B.
Observations
C.
Product analysis
D.
Expert judgment
Expert judgment
Which tool or technique is an examination of industry and specific vendor capabilities?
A.
Independent estimates
B.
Market research
C.
Analytical techniques
D.
Bidder conferences
Market research
An input used in developing the communications management plan is:
A.
Communication models.
B.
Enterprise environmental factors.
C.
Organizational communications,
D.
Organizational cultures and styles.
Enterprise environmental factors.
Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend
analysis are examples of which tool or technique?
A.
Expert judgment
B.
Forecasting methods
C.
Earned value management
D.
Analytical techniques
Analytical techniques
The Perform Quality Assurance process occurs in which Process Group?
A.
Executing
B.
Monitoring and Controlling
C.
Initiating
D.
Planning
Executing
Enterprise environmental factors are an input to which process?
A.
Control Scope
B.
Define Scope
C.
Plan Scope Management
D.
Collect Requirements
Plan Scope Management
Which process develops options and actions to enhance opportunities and reduce threats to
project objectives?
A.
Identify Risks
B.
Control Risks
C.
Plan Risk Management
D.
Plan Risk Responses
Plan Risk Responses
The process of establishing the policies, procedures, and documentation for planning, developing,
managing, executing, and controlling the project schedule is known as:
A.
Plan Schedule Management.
B.
Develop Project Charter.
C.
Develop Schedule.
D.
Plan Scope Management
Plan Schedule Management.
Which input to the Manage Stakeholder Engagement process is used to document changes that
occur during the project?
A.
Issue log
B.
Change log
C.
Expert judgment
D.
Change requests
Change log
An input to the Plan Stakeholder Management process is:
A.
The project charter.
B.
The stakeholder analysis.
C.
A communication management plan.
D.
A stakeholder register.
A stakeholder register.
| Page 1 out of 66 Pages |
| 1234567891011121314151617181920 |
Real-World Scenario Mastery: Our CAPM practice exam don't just test definitions. They present you with the same complex, scenario-based problems you'll encounter on the actual exam.
Strategic Weakness Identification: Each practice session reveals exactly where you stand. Discover which domains need more attention, before Certified Associate in Project Management exam day arrives.
Confidence Through Familiarity: There's no substitute for knowing what to expect. When you've worked through our comprehensive CAPM practice exam questions pool covering all topics, the real exam feels like just another practice session.