Free CAPM Practice Test Questions 2026

785 Questions


Last Updated On : 20-May-2026


Topic 1, Volume A

Reserve analysis is a tool and technique used in which process?


A.

Plan Risk Management


B.

Plan Risk Responses


C.

Identify Risks


D.

Control Risks





D.
  

Control Risks



Updates to organizational process assets such as procurement files, deliverable acceptances, and
lessons learned documentation are typical outputs of which process?


A.

Close Project or Phase


B.

Conduct Procurements


C.

Control Procurements


D.

Close Procurements





D.
  

Close Procurements



Risk categorization is a tool or technique used in which process?


A.

Plan Risk Responses


B.

Plan Risk Management


C.

Perform Qualitative Risk Analysis


D.

Perform Quantitative Risk Analysis





C.
  

Perform Qualitative Risk Analysis



A regression line is used to estimate:


A.

Whether or not a process is stable or has predictable performance.


B.

How a change to the independent variable influences the value of the dependent variable.


C.

The upper and lower specification limits on a control chart.


D.

The central tendency, dispersion, and shape of a statistical distribution.





B.
  

How a change to the independent variable influences the value of the dependent variable.



An input to Conduct Procurements is:


A.

Independent estimates.


B.

Selected sellers.


C.

Seller proposals.


D.

Resource calendars.





C.
  

Seller proposals.



What are the Project Procurement Management processes?


A.

Conduct Procurements, Control Procurements, Integrate Procurements, and Close
Procurements


B.

Estimate Procurements, Integrate Procurements, Control Procurements, and Validate
Procurements


C.

Plan Procurement Management, Conduct Procurements, Control Procurements, and Close
Procurements


D.

Plan Procurement Management, Perform Procurements, Control Procurements, and Validate
Procurements





C.
  

Plan Procurement Management, Conduct Procurements, Control Procurements, and Close
Procurements



Which tool or technique is used to develop the human resource management plan?


A.

Ground rules


B.

Expert judgment


C.

Team-building activities


D.

Interpersonal skills





B.
  

Expert judgment



Processes in the Planning Process Group are typically carried out during which part of the project
life cycle?


A.

Only once, at the beginning


B.

At the beginning and the end


C.

Once during each phase


D.

Repeatedly





D.
  

Repeatedly



The basis of identification for current or potential problems to support later claims or new
procurements is provided by:


A.

A risk urgency assessment.


B.

The scope baseline.


C.

 Work performance information.


D.

Procurement audits.





C.
  

 Work performance information.



Which Collect Requirements output links the product requirements to the deliverables that satisfy
them?


A.

Requirements documentation


B.

Requirements traceability matrix


C.

 Project management plan updates


D.

Project documents updates





B.
  

Requirements traceability matrix



Units of measure, level of precision, level of accuracy, control thresholds, and rules of
performance measurement are examples of items that are established in the:


A.

Cost management plan.


B.

Work performance information.


C.

Quality management plan.


D.

Work breakdown structure.





A.
  

Cost management plan.



Which type of dependency is established based on knowledge of best practices within a particular
application area or some unusual aspect of the project in which a specific sequence is desired,
even though there may be other acceptable sequences?


A.

External


B.

Internal


C.

Mandatory


D.

Discretionary





D.
  

Discretionary




Page 9 out of 66 Pages
PreviousNext
1234567891011121314151617181920
CAPM Practice Test Home

What Makes Our Certified Associate in Project Management Practice Test So Effective?

Real-World Scenario Mastery: Our CAPM practice exam don't just test definitions. They present you with the same complex, scenario-based problems you'll encounter on the actual exam.

Strategic Weakness Identification: Each practice session reveals exactly where you stand. Discover which domains need more attention, before Certified Associate in Project Management exam day arrives.

Confidence Through Familiarity: There's no substitute for knowing what to expect. When you've worked through our comprehensive CAPM practice exam questions pool covering all topics, the real exam feels like just another practice session.