Free PMP Practice Test Questions 2026

2131 Questions


Last Updated On : 17-Aug-2026


Topic 3: Exam Pool C

A project team is experiencing conflict between two team members. Team member A feels that team member B is always talking over team member. A and does not listen to any advice Team member B is not willing to listen to feedback

What should the project manager do to resolve the issue?


A. Move one of the team members to a different protect team


B. Review the ground rules for collaboration within the team


C. Report the performance issue to both of the team members' supervisors


D. Modify the communications management plan and resend it to the team





B.
  Review the ground rules for collaboration within the team

The customer wants to show their stakeholders a tangible outcome faster. This requires advancing a milestone.

Which two things should the project manager do? (Choose two)


A. Inform the customer that moving the milestone has a very high impact on project cost.


B. Escalate the Issue to senior management so they can impose a solution on the customer.


C. Convince the customer to keep the requirements as is and not move the milestone.


D. Review the customer's priorities regarding the desired requirements for the milestones.


E. Discuss which requirements can be delivered faster with the project team.





D.
  Review the customer's priorities regarding the desired requirements for the milestones.

E.
  Discuss which requirements can be delivered faster with the project team.

During a team meeting the project manager asks the team to complete a personality assessment to help everyone understand themselves and one another better. The project manager analyzes the results and realizes that more than one-half of team members are introverts

What should the project manager do?


A. Present brainstorming topics a day before the session so the team can reflect and contribute more fully during the session


B. Adjust the lighting and ambient sounds in the work and common areas to create a relaxing work atmosphere


C. Ensure the team understands that their input needs to be fully articulated and explained to all team members during daily standups


D. Require everyone to share personal details at the start of each team meeting to allow learn members to get to know one another





A.
  Present brainstorming topics a day before the session so the team can reflect and contribute more fully during the session

Vendor A submitted a bid for US$500,000. There is a 65% probability that the vendor will deliver behind schedule with a cost overrun of US$ 100,000. The vendor will come in ahead of schedule for a savings of US$50,000.

What should the project manager determine as the value of the vendor's bid?


A. US$650,000


B. US$452,500


C. US$547,500


D. US$582,500





C.
  US$547,500

A project requires testing of the final product to be done at another department's testing facility, which is known for having low availability. This situation could potentially impact the project schedule.

What should the project manager do next?


A. Update the risk register.


B. Update the issue log.


C. Update the lessons learned register.


D. Update the lessons learned register.





A.
  Update the risk register.

A team is developing an experimental program to be used by the public. What should the project manager do to ensure the desired benefits are achieved?


A. Ensure that the project team fully tests the program.


B. Ensure a review is done with a representative group of users.


C. Meet with government officials to review policy requirements.


D. Document the features fully and update the specifications.





B.
  Ensure a review is done with a representative group of users.

A new building project is in the middle of its life cycle. The municipality informs the project manager that due to new regulations, the parking lot around the project has to accommodate twice the number of cars than was initially planned.

What should the project manager do next?


A. Request the project sponsor to fund this change as it is a new regulation, then order the materials in order to start working.


B. Assess the impact of the required change and consult with the executive sponsors to determine the best course of action.


C. Ask the designers to start designing a solution for this new requirement while the project is running and determine the funding for this change.


D. Have the company's lawyers write to the municipality and reject the change as it was not part of the scope approved by the municipality.





B.
  Assess the impact of the required change and consult with the executive sponsors to determine the best course of action.

Organizational downsizing has resulted in the key subject matter expert (SME) resource leaving a multiyear project. What should the project manager do?


A. Update the stakeholder register.


B. Refer to the resource management plan.


C. Consult the project sponsor.


D. Modify the statement of work (SOV).





B.
  Refer to the resource management plan.

A team lead has been highly engaged and involved in a project and is operating without a chain of command or authority levels What is the team lead dang1?


A. Modeling directive leadership


B. Modeling commanding leadership


C. Modeling adaptive leadership


D. Modeling servant leadership





D.
  Modeling servant leadership

A project team has transitioned to full-time remote working. The project manager started noticing that some team members have not been completing their assigned tasks by the planned dates despite reminders during weekly team meetings. This has the potential for delaying the project delivery.

How should the project manager resolve this situation?


A. Communicate the delivery dates twice a week to the team members to ensure timelydelivery.


B. Set up review sessions with each of the team members to identify the root cause ofdelays.


C. Mentor the team members to work in a remote work environment to ensureproductivity.


D. Talk to the resource managers regarding the delay and request additional resources





B.
  Set up review sessions with each of the team members to identify the root cause ofdelays.

A protect manager has just finished planning for a project when the client adds a new project team member The project manager Knows that the new team member only works remotely and is not in the main office. In addition, the new team member engages with decisions quickly in a face-to-face environment, but is slow to respond otherwise.

How should the project manager reflect this in their planning?


A. Send out recurring onsite project meeting invites to ensure the team member's presence.


B. Update the project charter to include the new team member for this project.


C. Monitor the new team member's input to gauge their value to the project.


D. Include the team member in the stakeholder register and update the communications management plan.





D.
  Include the team member in the stakeholder register and update the communications management plan.

A project with multiple teams recently transitioned from a predictive approach to agile as requested by the product owner. Midway through implementation, a team member noticed there was no technical capability to support the current business requirement; therefore,the project will need to be reworked and the issue needs to be communicated to all stakeholders.

What should the agile project lead have done to avoid this situation?


A. Assessed the technical and organizational readiness for the project and identified risksat the beginning of the first iteration


B. Requested the product owner's approval to add an external expert to define theacceptance criteria


C. Defined a clear acceptance criteria at the initiation phase and continued with theproject


D. Increased the communications between the team member and the product owner





A.
  Assessed the technical and organizational readiness for the project and identified risksat the beginning of the first iteration


Page 58 out of 178 Pages
PreviousNext
313233343536373839404142434445464748495051525354555657585960616263646566676869707172737475767778798081828384
PMP Practice Test Home

What Makes Our Project Management Professional (2023 Version) Practice Test So Effective?

Real-World Scenario Mastery: Our PMP practice exam don't just test definitions. They present you with the same complex, scenario-based problems you'll encounter on the actual exam.

Strategic Weakness Identification: Each practice session reveals exactly where you stand. Discover which domains need more attention, before Project Management Professional (2023 Version) exam day arrives.

Confidence Through Familiarity: There's no substitute for knowing what to expect. When you've worked through our comprehensive PMP practice exam questions pool covering all topics, the real exam feels like just another practice session.