Topic 1: Exam Pool A
Team members are having a discussion with the project manager In the last retrospective
meeting, the team realized that the obsolete equipment could affect the next iteration of the
project The team recommends buying new equipment because it is critical to the success
of the final deliverable
What should the project manager do next?
A. Check the project budget to verify if there is enough contingency reserve
B. Review the cost management plan to determine how to address this issue
C. Tell the team members that more equipment is not part of the project's scope.
D. Submit a change request to increase the budget and buy new equipment
In a multinational multi location project with virtual teams a project manager has
established a project baseline The project manager discovers that multiple risk elements
have appeared. The project manager did not foresee these risks during the planning stage
of the project.
What should the project manager calculate to address this critical budgetary situation?
(Choose two)
A. Contingency control in the project and rebaseline
B. Mitigation control in the project
C. Benefits management control in the project
D. Integrated change control in the project
E. Currency exchange rate
During project execution, a project manager is informed that most of the project team members have enrolled in the newly implemented work-from-home company policy. How should the project manager reflect this change in the project?
A. Update the communication styles for enrolled team members in the communications management plan.
B. Update roles and responsibilities for enrolled team members in the responsibility assignment matrix (RAM)
C. Update the stakeholder engagement plan to include the emergency contact information for enrolled team members.
D. Update the resource calendar for enrolled team members in the resource management plan
While reviewing prototypes, the quality team found some deviations that do not affect the
mam functionality but have the potential to be an issue in the future To avoid major
problems in the future, the team recommends corrective actions that will require additional
funds The project is already struggling to stay on budget and has even used some of the
contingency reserves
What should the project manager do?
A. Ask the product designer why the deviation was not considered in the design phase
B. Report to the project sponsor that the product is working and the project is struggling with the budget.
C. Evaluate and initiate the change request process with the stakeholders
D. Ask the quality team to discard the sample and test again with a new sample
A project manager is managing a hybrid project After attending an iteration review, a
stakeholder tells the project manager that they are very busy and asks why these reviews
are held so frequently.
How should the project manager respond'?
A. Negotiate a reduced review attendance with the stakeholder and update the stakeholder engagement plan to reflect this reduced attendance
B. Discuss with the stakeholder the benefits of the hybrid project and how frequent reviews lead to greater value and less rework
C. Record the issue in the issue log and escalate the conflict to the project sponsor for assistance
D. Explain to the stakeholder that the stakeholder engagement plan requires theirattendance at all reviews
The team is working on a critical project deliverable and the project manager is concerned
about meeting the deadline There have been complaints from some stakeholders about
some of the team members' performance The project manager wants to understand the
situation and provide feedback to the team as soon as possible
What three actions should the project manager take to address this situation? (Choose
three)
A. Define team ground rules
B. Perform a retrospective session
C. Implement daily team meetings.
D. Request a manager performance review
E. Conduct an annual review.
A team is currently working on a mobile app solution. During sprint execution, one of the
developers requires clarification about the acceptance criteria for a particular task
What should the project manager do to obtain the information required by the developer?
A. Request direction from the project sponsor
B. Write an email to the client requesting clarification
C. Seek support from the development manager.
D. Work with the product owner to clarify the requirement
A project manager is working on the implementation of new phases in the production process of a regulated industry. Which two stakeholders can help the project manager determine and address compliance requirements? (Choose two)
A. Risk steering committee
B. Functional managers
C. Board of directors
D. Advisory team panel
E. Chief executive officer
The change control board (CCB) rejects a change request submitted by a subject matter
expert (SME) The SME refuses to accept this rejection and does not want to continue the
project without the change
What should the project manager have done to avoid this situation?
A. Requested that the sponsor approved the change request first.
B. Assessed the change's overall impact to the project before submission
C. Ensured that the change request was aligned with the project scope
D. Submitted the change request directly to the CCB
To estimate the costs of a new project that is similar to a project that was implemented last
year, the project manager meets with a group of experts from the previous project The
group uses a three-point estimating technique The project manager submits the estimated
budget to the project sponsor for approval The project sponsor, who is new to the
company, is concerned because the budget exceeded their expectations
What should the project manager do?
A. Review the organizational process assessment to determine if a contingency reserve was considered in the budget estimate
B. Review the historical information and lessons learned from last year’s project to justify the new budget estimate
C. Change the budgeting technique to a more accurate, bottom-up cost estimation.
D. Use soft skills to convince the project sponsor to approve the new budget estimate
In an advanced stage of a project a stakeholder who is not receiving the project status
report communicates this to the project manager After checking, the project manager
determines that the person is registered as a stakeholder but was not included in the
communications management plan.
What should the project manager do next1?
A. Update the communications management plan to include the missed stakeholder, and send the current project status documentation to this stakeholder
B. Inform the project sponsor that there are stakeholders who are not included in the communications management plan
C. Inform the stakeholder that the project team cannot provide information to anyone who is not registered in the project's communications management plan
D. Ask the stakeholder to get the project status report from another stakeholder listed in the communications management plan.
An agile project is in its eighth iteration out of 16 After the last iteration review, the team
members receive feedback from the security department about regulations with which the
project must comply
Which two actions should the project manager take? (Choose two)
A. Ask the team members to analyze the impact of including this regulation
B. Ask the stakeholders about the priority of this regulation
C. Ask the product owner to include the requirements in the product backlog
D. Ask the security department for details about regulations
E. Ask the team members to include the requirements in the next iteration
| Page 16 out of 48 Pages |
| 91011121314151617181920212223 |
| PMP Practice Test Home |
Real-World Scenario Mastery: Our PMP practice exam don't just test definitions. They present you with the same complex, scenario-based problems you'll encounter on the actual exam.
Strategic Weakness Identification: Each practice session reveals exactly where you stand. Discover which domains need more attention, before Project Management Professional (2023 Version) exam day arrives.
Confidence Through Familiarity: There's no substitute for knowing what to expect. When you've worked through our comprehensive PMP practice exam questions pool covering all topics, the real exam feels like just another practice session.