A company is initiating a project to enhance one of its existing products. All of its products are developed internally What should the project manager do?


A. Ensure the stakeholder engagement plan is accurate and properly documented.


B. Review the lessons learned from the previous project


C. Identify the risk of implementing the new solution and evaluate the impact on the project.


D. Create a lessons learned document for the initiation phase





B.
  Review the lessons learned from the previous project

During the implementation phase of a construction project, a key supplier went bankrupt and cannot supply the contracted material. This issue could affect the project schedule What should the project manager do first?


A. Update the issue log and act to minimize the impact


B. Update the schedule to include the delay


C. Add the risk and the delay to the risk register


D. Escalate to the management team for delay approval





A.
  Update the issue log and act to minimize the impact

During the implementation stage of a project. a newly appointed team leader approaches the project manager to verify the team's tasks and schedule. The work did not go as planned due to the team leader's lack of management experience. This could cause delays for the project.

What should the project manager do?


A. Ask the human resources director to appoint a senior team leader


B. Inform the project sponsor about the possible delay


C. Directly manage the project team to avoid project delays


D. Provide mentoring to the newly appointed team leader





D.
  Provide mentoring to the newly appointed team leader

After the project charter's approval the project manager needs to work on detailed project requirements, constraints and assumptions with stakeholders However, not all of the stakeholders are immediately available for a meeting in the short term.

What should the project manager do in order to gather the information needed from stakeholders?


A. Email, call, or meet with each stakeholder separately to obtain their input


B. Conduct a meeting to build the project management plan with the stakeholders who are available


C. Escalate to the project sponsor that not all stakeholders are available for a meeting


D. Meet with the project management team to build the project management plan before consulting stakeholders





A.
  Email, call, or meet with each stakeholder separately to obtain their input

One team member is not as active as the rest of the team during a brainstorming session The project manager has a separate conversation with the team member and learns that the team member is slightly hearing impaired The team member appreciates the project manager's concern The project manager then decides to change the time and room for the meeting to ensure everyone can participate

What interpersonal skill did the project manager use?


A. Networking


B. Emotional intelligence


C. Conflict management


D. Influencing





B.
  Emotional intelligence

A project sponsor commonly asks the project manager to skip project retrospectives due to time constraints However the project manager persists in running this critical ceremony by reducing the time for preparation and for discussion

What are two issues that these actions by the project manager could cause? (Choose two)


A. A lot of discussions that yield no results or possibly too many results


B. A lack of direction and motivation for the team in the workshop


C. Lessons learned from other teams to not be considered


D. Time management plan for the retrospective workshop to not be updated


E. A focus on the negative and a disinterest in further improvements





A.
  A lot of discussions that yield no results or possibly too many results

E.
  A focus on the negative and a disinterest in further improvements

In a newly formed project team one experienced team member is overwhelmed by the complexity of the tasks and is not happy with the project team. What should the project manager do?


A. Ask the team member to enter this potential schedule delay in the risk register.


B. Explain that the tasks are unavoidable and ask the team member to find a solution to overcome the challenges


C. Actively listen to the team member and identify ways to support their needs in completing the tasks.


D. Set up team-building activities with the project team members to reduce tension





C.
  Actively listen to the team member and identify ways to support their needs in completing the tasks.

During project execution, a conflict occurs between the project manager and one of the team members at every project team meeting The ongoing conflict is preventing tasks and deliverables from being completed The project manager contemplates changing their leadership style

What should the project manager do?


A. Review the set of responsibilities with the team member


B. Avoid the team member to prevent further conflicts


C. Escalate the situation to the project sponsor


D. Review the personnel skill documents





A.
  Review the set of responsibilities with the team member

The team has reported the following impediments at the daily standup meeting Drag each impediment on the left to the action that the project manager needs to take on the right






In a time-critical construction project, a misunderstanding occurred between the supervisor and the technician The misunderstanding turned into a major conflict and the technician has complained to the project manager that they cannot continue to work under the supervisor any longer. The supervisor cites the technicians poor performance as the reason for the conflict

How should the project manager resolve the problem?


A. Talk to the supervisor to tone down their approach and attitude.


B. Provide a just-in-time training to the technician to improve their skill set.


C. Use a direct, collaborative approach with the technician and supervisor.


D. Replace the technician with a high performing resource as time is critical





C.
  Use a direct, collaborative approach with the technician and supervisor.

A project manager is working on a software development project. A team member complains that since the project tasks are very simple, there is no reason to perform quality control The project manager understands that removing the quality management plan from the project will also help to save money, which is important to the customer

What should the project manager do?


A. Register starting the project without a quality management plan as a risk, and allocate the budget savings to the management reserve


B. Develop the quality management plan, as quality is as equally important as cost and schedule management.


C. Get confirmation from management that the team member has enough experienceto build software without quality control


D. Ask the customer to order an external quality audit after accepting the project deliverable, and decrease the budget of the project





B.
  Develop the quality management plan, as quality is as equally important as cost and schedule management.

The project is delayed due to the high amount of major changes requested by different stakeholders at different stages of the project If the project continues on the same path, it will consume twice the time and budget planned.

What two actions can the project manager take to be more cost effective? (Choose two)


A. Conduct a stakeholder analysis.


B. Reinforce team communication.


C. Update the project management plan with the new timeline


D. Adopt an incremental approach


E. Leverage work between team members





A.
  Conduct a stakeholder analysis.

D.
  Adopt an incremental approach


Page 11 out of 44 Pages
PreviousNext
4567891011121314151617
PMP Practice Test Home

What Makes Our Project Management Professional (2023 Version) Practice Test So Effective?

Real-World Scenario Mastery: Our PMP practice exam don't just test definitions. They present you with the same complex, scenario-based problems you'll encounter on the actual exam.

Strategic Weakness Identification: Each practice session reveals exactly where you stand. Discover which domains need more attention, before Project Management Professional (2023 Version) exam day arrives.

Confidence Through Familiarity: There's no substitute for knowing what to expect. When you've worked through our comprehensive PMP practice exam questions pool covering all topics, the real exam feels like just another practice session.