Topic 3, Volume C

Which schedule network analysis technique modifies the project schedule to account for limited
resources?


A.

Human resource planning


B.

Fast tracking


C.

Critical chain method


D.

Rolling wave planning





C.
  

Critical chain method



Which of the following is an output of the Monitor and Control Project Work process? 


A.

Change requests


B.

Performance reports


C.

Organizational process assets


D.

Project management plan





A.
  

Change requests



Which of the following statements correctly characterizes pull communication?


A.

It includes letters, memos, reports, emails, and faxes.


B.

It requires recipients to access communication content at their own discretion.


C.

It is the most efficient way to ensure a common understanding among all participants.


D.

It is primarily used when the volume of information to be transferred is minimal.





B.
  

It requires recipients to access communication content at their own discretion.



When would resource leveling be applied to a schedule model?


A.

Before constraints have been identified


B.

Before it has been analyzed by the critical path method


C.

After it has been analyzed by the critical path method


D.

After critical activities have been removed from the critical path





C.
  

After it has been analyzed by the critical path method



Which Knowledge Area is concerned with the processes required to ensure timely and appropriate
generation, collection, distribution, storage, retrieval, and ultimate disposition of project
information?


A.

Project Integration Management


B.

Project Communications Management


C.

Project Information Management System (PIMS)


D.

 Project Scope Management





B.
  

Project Communications Management



Which of the following tools or techniques is used for Estimate Activity Durations?


A.

Critical path method


B.

Rolling wave planning


C.

Precedence diagramming method


D.

Parametric estimating





D.
  

Parametric estimating



Information collected on the status of project activities being performed to accomplish the project
work is known as what?


A.

Project management information system


B.

Work performance information


C.

Work breakdown structure


D.

Variance analysis





B.
  

Work performance information



What is the number of stakeholders, if the project has 28 potential communication channels?


A.

7


B.

8


C.

14


D.

16





B.
  

8



Which of the following risk response strategies involves allocating ownership of a positive risk to a
third party?


A.

Mitigate


B.

Transfer


C.

Share


D.

 Avoid





C.
  

Share



Which activity is an input to the Conduct Procurements process?


A.

Organizational process assets


B.

Resource availability


C.

Perform Integrated Change Control


D.

Team performance assessment





A.
  

Organizational process assets



Which of the following investigates the likelihood that each specific risk will occur?


A.

Risk register


B.

Risk audits


C.

Risk urgency assessment


D.

Risk probability and impact assessment





D.
  

Risk probability and impact assessment



What is a hierarchically organized depiction of the identified project risks arranged by risk
category?


A.

Risk register


B.

Risk breakdown structure (RBS)


C.

Risk management plan


D.

Risk category





B.
  

Risk breakdown structure (RBS)




Page 30 out of 66 Pages
PreviousNext
2021222324252627282930313233343536373839
CAPM Practice Test Home

What Makes Our Certified Associate in Project Management Practice Test So Effective?

Real-World Scenario Mastery: Our CAPM practice exam don't just test definitions. They present you with the same complex, scenario-based problems you'll encounter on the actual exam.

Strategic Weakness Identification: Each practice session reveals exactly where you stand. Discover which domains need more attention, before Certified Associate in Project Management exam day arrives.

Confidence Through Familiarity: There's no substitute for knowing what to expect. When you've worked through our comprehensive CAPM practice exam questions pool covering all topics, the real exam feels like just another practice session.