Topic 3, Volume C
Which technique is used in Perform Quantitative Risk Analysis?
A.
Sensitivity analysis
B.
Probability and impact matrix
C.
Risk data quality assessment
D.
Risk categorization
Sensitivity analysis
Which illustrates the connection between work that needs to be done and its project team
members?
A.
Work breakdown structure (WBS)
B.
Network diagrams
C.
Staffing management plan
D.
Responsibility assignment matrix (RAM)
Responsibility assignment matrix (RAM)
Which tools or techniques will a project manager use for Develop Project Team?
A.
Negotiation
B.
Roles and responsibilities
C.
Recognition and rewards
D.
Prizing and promoting
Recognition and rewards
Which of the following is an input to Direct and Manage Project Execution?
A.
Requested changes
B.
Approved change requests
C.
Work performance information
D.
Implemented defect repair
Approved change requests
Which of the following is TRUE about most project life cycles?
A.
Staffing level is highest at the start.
B.
The stakeholders' influence is highest at the start.
C.
The level of uncertainty is lowest at the start.
D.
The cost of changes is highest at the start.
The stakeholders' influence is highest at the start.
An input required in Define Scope is an organizational:
A.
structure.
B.
process asset.
C.
matrix.
D.
breakdown structure.
process asset.
What cost control technique is used to compare actual project performance to planned or
expected performance?
A.
Cost aggregation
B.
Trend analysis
C.
Forecasting
D.
Variance analysis
Variance analysis
What is the term assigned to products or services having the same functional use but different technical characteristics?
A.
Scope
B.
Quality
C.
Specification
D.
Grade
Grade
When is a Salience Model used?
A.
In a work breakdown structure (WBS)
B.
During quality assurance
C.
In stakeholder analysis
D.
During quality control (QC)
In stakeholder analysis
Which of the following is contained within the communications management plan?
A.
An organizational chart
B.
Glossary of common terminology
C.
Organizational process assets
D.
Enterprise environmental factors
Glossary of common terminology
Which of the following is a tool and technique for Estimate Activity Durations?
A.
Parametric estimating
B.
Monte Carlo analysis
C.
Alternatives analysis
D.
Bottom-up estimating
Parametric estimating
Projects can be divided into phases to provide better management control. Collectively, what are
these phases known as?
A.
Complete project phase
B.
Project life
C.
The project life cycle
D.
Project cycle
The project life cycle
| Page 29 out of 66 Pages |
| 1920212223242526272829303132333435363738 |
| CAPM Practice Test Home |
Real-World Scenario Mastery: Our CAPM practice exam don't just test definitions. They present you with the same complex, scenario-based problems you'll encounter on the actual exam.
Strategic Weakness Identification: Each practice session reveals exactly where you stand. Discover which domains need more attention, before Certified Associate in Project Management exam day arrives.
Confidence Through Familiarity: There's no substitute for knowing what to expect. When you've worked through our comprehensive CAPM practice exam questions pool covering all topics, the real exam feels like just another practice session.