Which Manage Communications tool or technique focuses on identifying and managing barriers?


A.

Communication methods


B.

Information technology


C.

Communication models


D.

Information management systems





C.
  

Communication models



Which type of organizational structure is displayed in the diagram provided?



A.

Balanced matrix


B.

Projectized


C.

Strong matrix


D.

Functional





B.
  

Projectized



Outputs of the Control Communications process include


A.

expert judgment and change requests


B.

work performance information and change requests.


C.

organizational process asset updates and an issue log.


D.

project management plan updates and an issue log.





B.
  

work performance information and change requests.



In the Plan Procurement Management process, which source selection criteria analyzes if the
seller's proposed technical methodologies, techniques, solutions, and services meet the
procurement documents requirements?


A.

Technical approach


B.

Technical capability


C.

Business size and type


D.

Production capacity and interest





A.
  

Technical approach



Stakeholder communication requirements should be included as a component of:


A.

enterprise environmental factors


B.

organizational process assets


C.

 the project management plan


D.

 the stakeholder register





C.
  

 the project management plan



Which element does a project charter contain?


A.

Management reserves


B.

Work breakdown structure


C.

Stakeholder list


D.

Stakeholder register





C.
  

Stakeholder list



The following is a network diagram for a project

What is the critical path for the project?


A.

A-B-C-F-G-I


B.

A-B-C-F-H-I


C.

A-D-E-F-G-I


D.

A-D-E-F-H-I





A.
  

A-B-C-F-G-I



The following is a network diagram for a project

How many possible paths are identified for this project?


A.

3


B.

4


C.

6


D.

7





B.
  

4



The following is a network diagram for a project.

The free float for Activity H is how many days?


A.

4


B.

5


C.

10


D.

11





A.
  

4



Every project creates a unique product, service, or result that may be:


A.

tangible


B.

targeted


C.

organized


D.

variable





A.
  

tangible



Correlated and contextualized information on how closely the scope is being maintained relative to
the scope baseline is contained within:


A.

project documents updates.


B.

project management plan updates.


C.

change requests.


D.

work performance information.





D.
  

work performance information.



The most appropriate project life cycle model for an environment with a high level of change and
extensive stakeholder involvement in projects is:


A.

adaptive


B.

reflexive


C.

predictive


D.

iterative





A.
  

adaptive




Page 22 out of 66 Pages
PreviousNext
1213141516171819202122232425262728293031
CAPM Practice Test Home

What Makes Our Certified Associate in Project Management Practice Test So Effective?

Real-World Scenario Mastery: Our CAPM practice exam don't just test definitions. They present you with the same complex, scenario-based problems you'll encounter on the actual exam.

Strategic Weakness Identification: Each practice session reveals exactly where you stand. Discover which domains need more attention, before Certified Associate in Project Management exam day arrives.

Confidence Through Familiarity: There's no substitute for knowing what to expect. When you've worked through our comprehensive CAPM practice exam questions pool covering all topics, the real exam feels like just another practice session.