Which of the following contract types would be most beneficial to both parties in cases in which the scope of the project has a large number of unknowns?


A. Variable costs


B. Fixed costs


C. Front-loaded


D. Time and materials





D.
  Time and materials

Explanation: Time and materials contracts are flexible and beneficial when the project scope has many unknowns. They allow costs to be adjusted based on actual time and resources used, which is consistent with CompTIA Project+ recommendations for projects with uncertain requirements.

A PM learns about some communication issues with different stakeholders and team members. Which of the following should the PM do NEXT?


A. Escalate the communication issues.


B. Implement a communication platform.


C. Review the communication plan.


D. Talk with the head of the PMO.





C.
  Review the communication plan.

Explanation: The project manager should review the communication plan after learning about some communication issues with different stakeholders and team members. A communication plan is a document that defines and documents the communication goals, strategies, methods, channels, frequency, roles, and responsibilities for a project. A communication plan can help to facilitate effective and timely communication among all stakeholders involved in a project and avoid confusion, misunderstanding, or conflicts.

A project manager was not part of a contract negotiation. The project manager is concerned that stakeholders will expect the project to achieve deliverables requested in the RFP Which of the following documents should the project manager produce FIRST to start communication about the boundaries of the project?


A. Milestone chart


B. Work breakdown structure


C. Project charter


D. Detailed scope statement





C.
  Project charter

Explanation: The project manager should produce a project charter first to start communication about the boundaries of the project. A project charter is a document that formally authorizes a project and defines its high-level scope, objectives, assumptions, constraints, stakeholders, roles and responsibilities, and key deliverables. A project charter can help to communicate the project vision and expectations to all stakeholders and provide a basis for future project decisions.

A project team is defining operational training, discussing a go-live date, and describing the operational handoff. Which of the following best describes what the team is developing?


A. The project closeout report


B. A handover to operations


C. Phase-gate review documentation


D. A transition plan





D.
  A transition plan

Explanation: A transition plan is a document that outlines how the project deliverables will be transferred to the operations team or the end users, and how the project team will disengage from the project. It typically includes details such as operational training, go-live date, support arrangements, roles and responsibilities, and acceptance criteria. A transition plan is different from a project closeout report, which summarizes the project performance, lessons learned, and final status. A handover to operations is a process of transferring the project deliverables to the operations team, but it is not a document. A phase-gate review documentation is a set of documents that are used to evaluate the project progress and readiness to move to the next phase, but it is not related to the operational handoff. References = CompTIA Project+ PK0-005 Certification Study Guide, Chapter 14: Closing the Project, p. 409-410; [CompTIA Project+ Certification Exam Objectives], Domain 4: Project Closure, Objective 4.1: Compare and contrast various project closure activities.

A stakeholder raises a concern with a project manager because of the number of emails that have been received before a coding release. Which of the following actions should the project manager take next?


A. Inform the CCB to stop communication


B. Establish a RACI matrix


C. Escalate the communication issues


D. Revise the communication plan





D.
  Revise the communication plan

Explanation: When stakeholders express concerns about the volume of communication, it’s important to review and adjust the communication plan to ensure it meets the project’s needs and stakeholders’ preferences. A RACI matrix is useful for defining roles and responsibilities but does not address communication frequency or methods directly. Escalating the issue may not be necessary if it can be resolved by revising the plan. Informing the CCB (Change Control Board) to stop communication is not advisable as the CCB’s role is to oversee changes, not to manage day-to-day communications.

A project sponsor requires a system that is capable of providing integrated management of all the business's core functions. Which of the following systems is the project sponsor describing?


A. CMS


B. CRM


C. EDRMS


D. ERP





D.
  ERP

Explanation: ERP (Enterprise Resource Planning) systems are designed to integrate and manage all core functions of a business, such as finance, HR, and supply chain management. This aligns with CompTIA Project+ guidelines on selecting appropriate systems for organizational needs.

A project team wants to compare two potential vendors' costs and risks for completing project tasks. Which of the following visualizations will best facilitate this analysis?


A. Scatter diagram


B. Decision tree


C. Pareto chart


D. Histogram





B.
  Decision tree

Explanation: A decision tree helps in evaluating various choices and their potential outcomes, making it suitable for comparing vendors based on costs and risks. This aligns with CompTIA Project+ methodologies for decision-making tools and analysis.

Which of the following is a quality assurance tool?


A. Defining project goals


B. Identifying the root cause analysis


C. Assessing employee efficiency


D. Assessing skill gaps





B.
  Identifying the root cause analysis

Explanation: Identifying the root cause analysis. Identifying the root cause analysis is a quality assurance tool that can help to find and eliminate the underlying causes of quality problems or defects. Root cause analysis is a systematic process of asking why a problem occurred and tracing it back to its source. Root cause analysis can help to prevent recurrence of the same or similar problems, improve quality performance, and reduce costs and risks12

Which of the following best represents the project impact to a company's brand value?


A. The project is compliant with local and state laws and becomes the standard for new projects.


B. The project promotes new initiatives to expand its benefit to other communities


C. The project exceeds the sales quota for the third quarter and raises the bar for next periods.


D. The project meets the expected milestones and finishes on time and within budget.





B.
  The project promotes new initiatives to expand its benefit to other communities

Explanation: the brand of a project should deliver the message about its value and goals, and a proper brand helps the project get the necessary support and increases loyalty. The project that promotes new initiatives to expand its benefit to other communities is the one that best represents the project impact to a company’s brand value, as it shows the company’s vision, cause, and reputation.

A project manager needs to update the project sponsor and senior stakeholders about the progress of a project. Which of the following tools will the project manager MOST likely use?


A. Dashboard


B. Gantt chart


C. Work breakdown structure


D. Requirements Traceability Matrix





A.
  Dashboard

Explanation: A dashboard is a tool that the project manager will most likely use to update the project sponsor and senior stakeholders about the progress of a project. A dashboard is a graphical tool that displays key performance indicators (KPIs), metrics, and data related to a project using charts, graphs, tables, or other visual elements. A dashboard can help to provide a quick and easy overview of the project status and performance and highlight any issues or risks that need attention.

During the project initiation phase, a project manager needs to construct a project schedule and show the project dependencies. Which of the following should the project manager use for this task?


A. Waterfall method


B. Simulation method


C. Precedence diagramming method


D. Cost ratio analysis





C.
  Precedence diagramming method

Explanation: The Precedence Diagramming Method (PDM) is used to visually represent tasks, dependencies, and sequencing in a project schedule. This technique is consistent with CompTIA Project+ guidelines for planning and managing project timelines.

A project manager, who finished a project some time ago, keeps receiving questions from another project manager who is currently leading a similar project. Which of the following is the most likely cause of this situation?


A. The retrospective session feedback was not communicated properly.


B. The project resources were released ahead of time.


C. The documentation was not archived as per the PMO standards.


D. The validation of deliverables is running behind schedule.





C.
  The documentation was not archived as per the PMO standards.

Explanation: Archiving project documentation is an important process to ensure that the project information is stored, retrieved, and updated in a consistent and efficient manner1. It also helps to meet legal requirements, enable long-term analysis, and support new projects and team members1. If the documentation was not archived as per the PMO standards, it would be difficult for the current project manager to find the relevant documents and learn from the previous project. This would cause the current project manager to keep asking questions to the previous project manager, who may not have all the answers or may not be available. Therefore, the most likely cause of this situation is that the documentation was not archived as per the PMO
standards. References = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 14: Closing the Project, page 403; How to Archive a Completed Project: A Guide for PMOs, Introduction and Benefits sections.