While working in a collaborative, online brainstorming session, team members send private messages to the facilitator about challenges understanding others when they are speaking due to accents and background noises. Which of the following should the facilitator do to overcome the challenges?
A. Instruct the team members to set their speakers to maximum volume and mute their microphones.
B. Require everyone to turn on their cameras and use the same background filter.
C. Encourage the use of the chat and use plain language when speaking.
D. Allow one person to speak at a time after receiving acknowledgment from the facilitator.
A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organization's reluctance could jeopardize the success of the project. Which of the following steps should be taken to understand the adoption issues and gain organizational acceptance of the initiative? (Select TWO).
A. Train users on the proper use of the system.
B. Escalate the issue to the CCB
C. Hold sessions to understand user challenges.
D. Track system usage and report user activity.
E. Log the issue in the project risk register.
F. Create a memorandum of acceptable use.
A PM is working on a strategy to store records. Which of the following dements must be included in this plan? (Select TWO)
A. Data management
B. Issue management
C. Work breakdown structure
D. Document management
E. Communication management
F. Risk management
A project manager is assigned to a multinational project with team members from different continents. Which of the following is the MOST important aspect for the project manager to consider?
A. Resource allocation
B. Communication security
C. Technological factors
D. Cultural differences
A project manager is receiving reports of the actual project expenditures and, based on this information, is making adjustments to the budget. In which of the following phases does this occur?
A. Planning
B. Closure
C. Initiation
D. Execution
During the execution of a project, a project manager wanted to discover how the number of
worked hours was affecting the quality of given tasks. For a two-month period, the following
data was documented:
Average worked hours
Which of the following describes the result?
A. A negative correlation exists between the number of mistakes and the working hours
B. No correlation exists between the number of mistakes and the working hours
C. A low correlation exists between the working hours and the number of mistakes.
D. A positive correlation exists between the number of mistakes and the working hours.
A PM needs to calculate the progress of the whole project scope for a presentation to the sponsor. Which of the following is the first document the PM should update?
A. Project network diagram
B. Gantt chart
C. Issue log
D. Risk report
A project manager is in the process of evaluating the probability and impact of a risk by assigning numbers such as a monetary value. Which of the following is the project manager using?
A. Monte Carlo simulation
B. Root cause analysis
C. Quantitative risk analysis
D. Risk response analysis
A project manager buys an extended warranty for a set of servers. Which of the following risk management strategies is the manager using?
A. Transfer
B. Avoid
C. Accept
D. Mitigate
A key stakeholder recommends to a senior developer that a new feature be added. The new feature is not part of the current requirement documentation. Which of the following is MOST likely happening?
A. Scope creep
B. Collecting requirements
C. Decision-making
D. Project change
In order to complete a major project deliverable, very specialized resources are required for some tasks. The PM failed to take into consideration during planning that the required resources would be available for fewer hours than required. Which of the following should the PM do first to make schedule changes?
A. Add a new risk.
B. Perform an impact analysis.
C. Escalate to the sponsor.
D. Raise a change request.
A project team gathers weekly to review its progress. Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments?
A. Status report
B. Project plan
C. Change log
D. Meeting minutes
Page 11 out of 31 Pages |
Previous |