MSP-Practitioner Practice Test Questions

52 Questions


Who is accountable for approval to proceed?


A. SRO


B. Sponsoring Group


C. Group of directors


D. Programme board





A.
  SRO

Explanation:

In project and programme governance (e.g., PRINCE2, MSP), accountability for approval to proceed typically lies with the Senior Responsible Owner (SRO). Here’s why:

1.Role of the SRO:
The single accountable individual for the programme/project’s success.
Owns the business case and approves key milestones (e.g., initiation, stage gates).
Ensures alignment with organizational strategy.
2.Why Not Other Options?
B. Sponsoring Group → Provides oversight but not final approval (supports the SRO).
C. Group of Directors → May influence decisions but lacks singular accountability.
D. Programme Board → Governs execution but delegates approval authority to the SRO.
3.Key Difference:
Accountability vs. Responsibility: The SRO is accountable for approvals, while others (e.g., boards) share responsibility.

When it is found that an acceptable Business Case is not emerging, which of the following is NOT one of the normal options?


A. Seek further funding for the programme


B. Design a Blueprint that is less ambitious


C. Close the Programme


D. Find a different approach to delivering the Blueprint





A.
  Seek further funding for the programme

Explanation:

When a Business Case is not emerging — meaning the program cannot demonstrate value, viability, or justification — the organization needs to reassess its scope, delivery method, or feasibility.
The normal options in this scenario are focused on realignment or termination, not simply increasing investment.

Common and appropriate options include:

B. Design a Blueprint that is less ambitious
Reduces scope and cost to fit what is justifiable.
C. Close the Programme
If no justifiable case can be made, closure is the responsible action.
D. Find a different approach to delivering the Blueprint
Changing delivery strategy (e.g., agile, incremental) may make the case viable.

Why A. Seek further funding is NOT a normal option:
Simply seeking more funding without a viable Business Case is not good governance.
Throwing more money at a failing or unjustified initiative increases risk and waste.
MSP and other governance frameworks emphasize value for money and justification at all times.
Therefore, A is not a valid or normal response when a Business Case is weak or not emerging.

Which of the following statements best defines 'transformational Flow'?


A. Common factors of success derived from lessons learned in programmes that had both positive and negative results


B. Allow organizations to put in place right leadership, delivery team, robust organization structures and controls


C. Provides a route through lifecycle of a programme, from its conception through to delivering new capability


D. Temporary flexible organization created to coordinate, direct and oversee implementation of set of related projects





C.
  Provides a route through lifecycle of a programme, from its conception through to delivering new capability

Explanation

Transformational Flow is a core concept in Managing Successful Programmes (MSP). It defines the structured progression a programme follows from its initial conception through to the delivery of new capabilities, transition to outcomes, and realization of benefits.

Why Option C Is Correct:
It describes the end-to-end lifecycle of a programme.
Ensures that transformation is planned, governed, and executed effectively.
Guides the programme through phases such as Identifying, Defining, Managing Tranches, and Closing.
As confirmed by the MSP Practitioner guide:
“Transformational Flow in MSP defines the route a programme follows through its lifecycle—from initial conception, through delivery of new capabilities, transitioning to desired outcomes, realizing benefits, and finally closing the programme.”

Why Other Options Are Incorrect:

A. Common factors of success…
Refers to lessons learned, not the lifecycle structure.
B. Leadership and controls…
Describes governance setup, not the transformational flow.
D. Temporary flexible organization…
Describes a programme structure, not the flow itself.

Which of below sentences describes Project Brief?


A. List of all projects that will be part of programme


B. Control framework for programme


C. Control framework for projects


D. Describes purpose, cost, time, performance requirements and constraints of a project





D.
  Describes purpose, cost, time, performance requirements and constraints of a project

Explanation:

A Project Brief is a key document in project management that provides a high-level overview of what a project aims to achieve. It defines the scope, objectives, constraints, and key deliverables — serving as the foundation for more detailed planning.

A Project Brief typically includes:
Purpose and objectives of the project
Estimated cost and budget range
Expected timeline or delivery schedule
Performance requirements (quality, scope, KPIs)
Constraints (e.g., regulatory, technical, or resource limits)
Initial risks and assumptions

Hence, Option D is the most accurate definition.

Why the other options are incorrect:

A. List of all projects that will be part of programme
➤ That refers to a Programme Project Dossier or Portfolio, not a single project brief.
B. Control framework for programme
➤That's part of the Programme Governance Strategy or Programme Plan.
C. Control framework for projects
➤ That would refer to a Project Initiation Document (PID) or Project Plan, not the brief.

In delivering the capability, who is responsible for aligning projects with benefits realization?


A. BCM


B. Programme Manager


C. Both


D. None





C.
  Both

Explanation:

In programme management (e.g., MSP® – Managing Successful Programmes), both the Programme Manager and the Business Change Manager (BCM) play complementary roles in ensuring that projects are aligned with benefits realization.

Roles and Responsibilities:

Programme Manager:
Oversees the delivery of capability through coordinated projects.
Ensures that project outputs align with the blueprint and benefits profiles.
Works closely with the BCM to ensure that projects remain aligned with business needs.

Business Change Manager (BCM):
Responsible for realizing the benefits from project outputs in the business environment. Ensures that the change is embedded, and outcomes are achieved.
Advises on business readiness and drives transition activities.
✅ Together, the Programme Manager and BCM ensure that the projects deliver what the business needs and that those outputs translate into realized benefits.

Why the other options are incorrect:
A. BCM – While the BCM is responsible for benefit realization, they cannot do it alone without coordination with the Programme Manager.
B. Programme Manager – Responsible for delivery, but not solely accountable for benefits realization in the business.
D. None – ❌ Incorrect, both roles are explicitly accountable.

Which of following groups can be a stakeholder for building a city programme?


A. Employees


B. Political leadership


C. People interested in being residents


D. All of above





D.
  All of above

Explanation:
A city-building programme impacts diverse groups, making all listed parties stakeholders with varying interests and influence:

1.Employees (Option A)
City staff, construction workers, planners who execute the programme.
Interest: Job security, working conditions.

2.Political Leadership (Option B)
Mayors, council members funding/approving projects.
Interest: Public approval, re-election.

3.Potential Residents (Option C)
Future homeowners/renters affected by housing, transit, or amenities.
Interest: Affordability, quality of life.

Why "All of Above"?
Stakeholder theory (Freeman, 1984) defines stakeholders as any group affected by or influencing an initiative.
City programmes require balancing these interests (e.g., public consultations).

Which of following is input for 'managing the tranches'?


A. Programme preparation plan


B. Programme Brief


C. Approval to proceed


D. Assurance review reports





C.
  Approval to proceed

Explanation

In the MSP (Managing Successful Programmes) framework, “Managing the Tranches” is the process that governs how a programme is delivered in manageable phases. To begin managing a tranche, the programme must have received formal authorization to proceed—this is known as “Approval to Proceed.”

Why Option C Is Correct:
Approval to Proceed is a trigger input for initiating a tranche.
It confirms that the programme has passed necessary reviews and is ready to move into execution.
This input ensures that governance, resources, and plans are in place for the tranche to begin.

Why Other Options Are Incorrect:

A. Programme Preparation Plan
Used earlier during programme setup—not a direct input for managing tranches.
B. Programme Brief
Created during programme identification—not relevant at the tranche level.
D. Assurance Review Reports
These are outputs or supporting documents—not primary inputs to initiate tranche management.

Who reviews Business Case?


A. Sponsoring Group


B. SRO


C. Programme Manager


D. BCM





A.
  Sponsoring Group

Explanation:

In programme governance (e.g., MSP® - Managing Successful Programmes), the Sponsoring Group is responsible for reviewing and approving the Business Case. Here’s why:

1.Role of the Sponsoring Group:
Represents senior leadership (e.g., executives, investors).
Ensures the Business Case aligns with strategic objectives.
Validates financial viability and risk appetite.

2.Why Not Others?

B. SRO (Senior Responsible Owner):
Owns the Business Case but doesn’t approve it (the Sponsoring Group does).
C. Programme Manager:
Drafts/updates the Business Case but lacks authority to approve.
D. BCM (Business Change Manager):
Focuses on benefits realization, not Business Case governance.

Who produces Business Case?


A. Sponsoring Group


B. SRO


C. Programme Manager


D. BCM





C.
  Programme Manager

Explanation:

In programme management frameworks like MSP® (Managing Successful Programmes), the Programme Manager is responsible for producing and maintaining the Business Case, though collaboration with other roles is essential. Here's the detailed breakdown:

Roles and Responsibilities:

1.Programme Manager (Correct Answer - C)
Leads the development of the Business Case, ensuring it includes:
Costs, benefits, risks, and timelines.
Alignment with organizational strategy.
Updates it regularly as the programme evolves.

2.Other Roles' Involvement:

SRO (Senior Responsible Owner - B):

Provides strategic direction and owns accountability for the Business Case.
Approves the final version but doesn't draft it.

Sponsoring Group (A):
Reviews and approves the
Business Case but doesn't create it. BCM (Business Change Manager - D):
Contributes to benefits realization plans but isn't responsible for the Business Case itself.

Why Not the Other Options?

A (Sponsoring Group): They govern and approve but don't produce.
B (SRO): They're accountable but delegate the creation to the Programme Manager.
D (BCM): They focus on implementing changes, not justifying the programme.

Which of the following is NOT normally a characteristic of the Vision Statement?


A. It must describe a desirable future


B. It is short


C. Key benefits are implicit


D. It must be time dependent





D.
  It must be time dependent

Explanation:

A Vision Statement is meant to describe a desirable future state for an organization. It is typically:

Aspirational and inspirational
Concise and memorable
Focused on long-term direction
Often includes implicit benefits or outcomes
However, it is not normally time-dependent. Unlike goals or objectives, which are tied to specific timelines, a vision statement is meant to be timeless and enduring, serving as a guiding star rather than a deadline-driven target.

Why the Other Options Are Characteristics of a Vision Statement:

A. Describes a desirable future
Core purpose of a vision statement.
B. It is short
Vision statements are typically concise and easy to remember.
C. Key benefits are implicit
Vision statements often imply benefits without listing them explicitly.

Which of the following is a KEY attribute for a Programme Manager?


A. Have ongoing operational responsibilities within their business area


B. Change management skills


C. A good knowledge of project management approaches


D. Have access to key stakeholders





B.
  Change management skills

Explanation:

A Programme Manager is responsible for coordinating multiple related projects to deliver strategic business outcomes. In doing so, one of their most critical responsibilities is to manage change — ensuring that new capabilities are adopted, benefits are realized, and stakeholders are aligned throughout the programme lifecycle.

Why B. Change management skills is correct:
A Programme Manager operates at a strategic and tactical level, and must:
Navigate organizational change
Coordinate business transformation
Align delivery with evolving business needs
They must understand the people side of change, including resistance, communication, training, and engagement strategies.

These skills are central to successful programme delivery, making Option B the key attribute.

Why the other options are less suitable:

A. Have ongoing operational responsibilities within their business area
Not ideal — Programme Managers should be focused on delivery, not bogged down with day-to-day operations.
C. A good knowledge of project management approaches
Helpful, but not a key attribute — they coordinate projects, not manage them directly. They need broader skills beyond project management.
D. Have access to key stakeholders
Important, but more of a requirement for success, not a personal attribute.

For a business transformation programme, which of scenarios will lead to high probability of success?


A. Process change affecting technology and structures


B. New products or services


C. Internal, external and customer behavior


D. Changing historical work practices





C.
  Internal, external and customer behavior

Explanation:

A business transformation programme succeeds when it addresses holistic change across people, processes, and ecosystems. Here’s why Option C (focusing on behavior) is the key to high success probability:

Why Option C is Correct?

1.Behavior Drives Adoption:
Internal: Employees must embrace new ways of working (e.g., agile mindset).
External: Partners/suppliers need to align (e.g., API integrations).
Customer: Buy-in ensures ROI (e.g., adopting a new app feature).

2.MSP®/Prosci Best Practices:
70% of transformations fail due to resistance to change (Kotter).
Programmes targeting behavior (e.g., training, incentives) see 6x higher success rates (Prosci).

Why Not Other Options?

A. Process/tech/structures → Necessary but useless without behavior change.
B. New products → Easy to build, hard to scale without customer adoption.
D. Historical practices → Too narrow (focuses only on internal legacy).


Page 1 out of 5 Pages