Which of the following forms of data is required for rough-cut capacity planning (RCCF)?
A. Current work in process (WIP)
B. Resource requirements plan
C. Critical work center availability
D. Work center queues
Explanation: Rough-cut capacity planning (RCCP) is a long-term capacity planning
technique that validates the master production schedule (MPS) by comparing the required
capacity and the available capacity of critical resources. Critical resources are those that
have the most impact on the production process, such as machines, labor, or materials.
RCCP helps to identify any potential imbalances or bottlenecks in the production system
and to adjust the MPS or the resource availability accordingly.
To perform RCCP, one of the forms of data that is required is critical work center
availability. A work center is a location where one or more resources perform a specific
operation or a group of operations. A critical work center is a work center that has a high
utilization rate, a low flexibility, or a high influence on the production output. Critical work center availability is the amount of time or capacity that a critical work center can offer for
production activities. Critical work center availability can be affected by factors such as
shifts, holidays, maintenance, breakdowns, or setups. RCCP uses critical work center
availability to determine whether there is enough capacity to meet the planned production.
Current work in process (WIP) is not a form of data that is required for RCCP. WIP is the
inventory of partially finished goods that are waiting for further processing or assembly.
WIP is not relevant for RCCP, as RCCP focuses on the future demand and capacity, not
the current inventory status.
Resource requirements plan is not a form of data that is required for RCCP. Resource
requirements plan is the output of RCCP, not the input. Resource requirements plan is a
report that shows the projected load and capacity of each critical resource over a planning
horizon. Resource requirements plan can help to identify any gaps or surpluses in capacity
and to take corrective actions.
Work center queues are not a form of data that is required for RCCP. Work center queues
are the waiting lines of jobs or orders at a work center. Work center queues are an indicator
of short-term capacity issues, such as delays, backlogs, or congestion. Work center
queues are not relevant for RCCP, as RCCP focuses on the long-term capacity planning,
not the short-term scheduling.
References := Guide to Rough-Cut Capacity Planning | Smartsheet, Guide to Rough Cut
Capacity Planning - Definition and Example, ROUGH-CUT CAPACITY PLANNING -
Operations Management: An Integrated …, Rough-cut Capacity Planning - Infor
Documentation Central
The approved output of the distribution requirements planning (DRP) process is an input to which of the following planningprocesses?
A. Strategic
B. Business
C. Master production 0
D. Final assembly
Explanation: The approved output of the distribution requirements planning (DRP)
process is an input to the master production planning (MPS) process. The DRP process
determines the quantity and timing of finished goods to be delivered to each distribution
center or warehouse to meet customer demand1. The output of the DRP process is a
distribution schedule that specifies the planned delivery dates and quantities of products2. The distribution schedule is then used as an input to the MPS process, which
determines the quantity and timing of end items to be produced at each manufacturing
facility3. The MPS process balances the demand from the distribution schedule with the
available capacity and resources of the production system3. The output of the MPS
process is a master production schedule that specifies the planned production dates and
quantities of end items3.
References: CPIM Part 2 Exam Content Manual, Domain 4: Plan and Manage Supply,
Section 4.1: Supply Management Concepts and Tools, p. 33-34.
The production plan relates to a firm's financial planning because it is used to:
A. calculate standard product costs.
B. determine variable costs.
C. project payroll costs.
D. identify future cash needs.
Explanation: The production plan is a statement of the resources needed to meet the
aggregate demand plan over a medium-term horizon. The production plan is the output of
the supply planning step in the sales and operations planning (S&OP) process. The
production plan relates to a firm’s financial planning because it is used to identify future
cash needs. Cash needs are the amount of money that a firm requires to operate and grow
its business. Cash needs can be influenced by various factors, such as sales revenue, cost
of goods sold, operating expenses, capital expenditures, inventory levels, accounts
receivable, accounts payable, and taxes. The production plan can help to estimate the
cash inflows and outflows associated with these factors, and to determine the optimal
balance between them. The production plan can also help to identify the potential sources
and uses of cash, such as borrowing, investing, or paying dividends. By identifying future
cash needs, the production plan can help to improve the firm’s liquidity, profitability, and
solvency.
References: CPIM Exam Content Manual Version 7.0, Domain 4: Plan and Manage
Supply, Section 4.1: Develop Supply Plans, Subsection 4.1.2: Describe how to develop a
production plan (page 36).
An advantage of activity-based costing (ABC) is:
A. it allows raw material costs to be allocated on a per unit basis.
B. it uses cost drivers to allocate costs to products.
C. it is easier to establish standard costs.
D. it enables overhead costs to be allocated evenly across all products.
Explanation: Activity-based costing (ABC) is a method of allocating costs to products or
services based on the activities that consume resources in the production or delivery
process. ABC identifies the cost drivers, which are the factors that cause or influence the
amount of resources used for each activity. ABC then assigns costs to products or services
based on the amount of cost drivers they use. An advantage of ABC is that it uses cost
drivers to allocate costs to products, which provides a more accurate and realistic picture of
the cost structure and profitability of each product or service. ABC helps to identify the
value-added and non-value-added activities, and to eliminate or reduce the waste and
inefficiency in the process. ABC does not allow raw material costs to be allocated on a per
unit basis, as raw material costs are usually considered as direct costs that can be traced
to each product or service. ABC does not make it easier to establish standard costs, which
are the predetermined or expected costs of producing or delivering a product or service.
ABC does not enable overhead costs to be allocated evenly across all products, as
overhead costs are the indirect costs that cannot be traced to each product or service. ABC
allocates overhead costs based on the cost drivers, which may vary for different products
or services. References: CPIM Exam Content Manual Version 7.0, Domain 8: Manage
Quality, Continuous Improvement, and Technology, Section 8.2: Continuous Improvement
Concepts, p. 46; Activity-Based Costing (ABC) Definition; Activity-based costing.
Given the information below, reducing which measure by 10% would contribute most to shortening the cash-to-cash cycletime?
A. Accounts receivable
B. Inventory value
C. Accounts payable
D. Cost of capital
Explanation: The cash-to-cash cycle time is a financial metric that measures the time it takes for a company to convert its cash outflows into cash inflows. The cash-to-cash cycle time is calculated by adding the days of inventory outstanding (DIO), the days of sales outstanding (DSO), and the days of payablesoutstanding (DPO), and then subtracting the days of payables deferred (DPD). The cash-to-cash cycle time can be shortened by reducing any of the components, except for DPD, which should be increased. Reducing which measure by 10% would contribute most to shortening the cash-to-cash cycle time depends on the relative values of each component.
Marketing has requested a significant change in the mix for a product family. The requested change falls between thedemand and the planning time fences. The most appropriate action by the master scheduler is to:
A. reject the request
B. accept the request.
C. forward the request to senior management.
D. check the availability of required material.
Explanation: The most appropriate action by the master scheduler is to forward the
request to senior management. According to the Time Fence Control (MRP and Supply
Chain Planning Help) - Oracle, the demand time fence is a period within which the planning
process does not consider forecast demand when calculating actual demand, and the
planning time fence is a period within which the planning process does not alter the current
material plan or master schedule. The master scheduler can make changes to the master
schedule within the planning time fence, but only with approval from senior management.
The request from marketing falls between the demand and the planning time fences, which
means that it may affect the current material plan or master schedule, as well as the
capacity and resource requirements of the production system. Therefore, the master
scheduler should forward the request to senior management, who can evaluate the impact
and feasibility of the request, and decide whether to approve or reject it.
In a lean environment, the batch-size decision for planning "A" items would be done by:
A. least total cost.
B. min-max.
C. lot-for-lot (L4L).
D. periodic order quantity.
Explanation: In a lean environment, the batch-size decision for planning “A” items would
be done by lot-for-lot (L4L). A lean environment is a production system that aims to
eliminate waste and maximize value by applying the principles and practices of lean
manufacturing1. “A” items are the most important items in an inventory system, based on
the Pareto principle or the 80/20 rule, which states that 80%of the effects come from 20%
of the causes2. Lot-for-lot (L4L) is an inventory ordering policy that orders exactly the
quantity needed to meet the demand for each period3.
The reason why L4L is the preferred batch-size decision for planning “A” items in a lean
environment is because it minimizes the inventory holding costs and reduces the risk of
obsolescence or deterioration of the items3. L4L also supports the concept of pull
production, which is a key element of lean manufacturing. Pull production is a method of
controlling the flow of materials and information by producing only what is requested by the
downstream customers or processes4. L4L aligns the production and consumption rates of
“A” items, which are typically high-demand and high-value items, and avoids
overproduction or underproduction. L4L also enables faster feedback and learning, as well
as better responsiveness to customer needs and expectations.
The other options are not as suitable for planning “A” items in a lean environment. Least
total cost is an inventory ordering policy that orders the quantity that minimizes the sum of
ordering costs and holding costs5. However, this policy does not consider the demand
variability or customer service level, and may result in large batch sizes that increase
inventory levels and waste. Min-max is an inventory ordering policy that orders a fixed
quantity whenever the inventory level falls below a minimum level6. However, this policy
does not reflect the actual demand or consumption rate, and may result in excess inventory
or stockouts. Periodic order quantity is an inventory ordering policy that orders a variable
quantity at fixed time intervals. However, this policy does not synchronize the production
and consumption rates, and may result in mismatched supply and demand.
References: Lean Manufacturing - Definition & Principles - ASQ; Pareto Principle -
Definition & Examples - Investopedia; Lot-for-Lot (L4L) Definition | Operations & Supply
Chain Dictionary; Pull Production - Definition & Examples - ASQ; Economic Order Quantity
(EOQ) Definition - Investopedia; Min-Max Inventory Management: Definition & Examples -
Video & Lesson Transcript | Study.com; [Periodic Order Quantity (POQ) Definition |
Operations & Supply Chain Dictionary].
Staging in a manual system corresponds to which of the following functions in a computer system?
A. Order release
B. Allocation
C. Dispatching
D. Bill-of-material explosion
Explanation: Staging in a manual system corresponds to dispatching in a computer
system. Staging is the process of preparing and moving materials or components to the
point of use or consumption in a production system1. Staging can be done manually by
workers who physically move the items from storage areas to workstations, or
automatically by conveyors, robots, or other devices2. Dispatching is the process of
authorizing and releasing work orders or tasks to the production system3. Dispatching can
be done manually by supervisors who assign work to workers, or automatically by
computer systems that use algorithms or rules to prioritize and schedule work4. Both
staging and dispatching are functions that facilitate the flow of materials and information in
a production system and ensure that the right items are available at the right time and
place.
References: CPIM Part 2 Exam Content Manual, Domain 6: Plan, Manage, and Execute
Detailed Schedules, Section 6.1: Detailed Scheduling Concepts and Tools, p. 75-
76; Staging (manufacturing) - Wikipedia; Staging - an overview | ScienceDirect
Topics; Dispatching - an overview | ScienceDirect Topics; Dispatching: Meaning,
Objectives, Importance and Procedure.
Operations strategy:
A. is a bottom-up reflection of what the whole group or business wants to do.
B. involves translating market requirements into operations decisions.
C. involves exploiting operations capabilities in the global market.
D. is a top-down activity where operations improvements cumulatively build strategy.
Explanation: Operations strategy is the process of aligning the operations function with the
strategic goals of the organization. It involves translating market requirements into
operations decisions that support the competitive priorities of the organization. Operations
strategy is not a bottom-up reflection of what the whole group or business wants to do, but rather a top-down alignment of the operations function with the overall business strategy.
Operations strategy is not a top-down activity where operations improvements cumulatively
build strategy, but rather a deliberate and coherent plan that guides the design and
management of the operations system. Operations strategy is not only about exploiting
operations capabilities in the global market, but also about developing and sustaining those
capabilities in response to the changing market needs.
References := What Is an Operations Strategy? Definition and Benefits, Operations
Strategy: Definition And Impact On Projects - monday.com, Operations Strategy: Definition,
Example & Strategies In 2022
Which of the following inventory management techniques is most responsive to changes in demand levels?
A. Two-bin system
B. Periodic review system
C. Cycle counting
D. ABC classification
Explanation: A two-bin system is a type of inventory management technique that uses two
containers or bins to store and replenish items. When the first bin is empty, the second bin
is used to supply the demand while the first bin is reordered. A two-bin system is most
responsive to changes in demand levels because it triggers replenishment orders based on
actual consumption rather than fixed time intervals or reorder points. A two-bin system can
reduce stockouts, improve service levels, and lower inventory costs.
References: CPIM
Exam Content Manual Version 7.0, Domain 5: Plan and Manage Inventory, Section 5.2:
Implement Inventory Plans, Subsection 5.2.3: Describe how to implement inventory
replenishment techniques (page 46).
The major contribution of the production plan is to:
A. establish demand by end item.
B. provide authorization for the master schedule.
C. identify key resources to support the master schedule.
D. establish the weekly build schedule.
Explanation: According to the web search results, the production plan is a long-term plan
that establishes the quantity and timing of the end products to be produced by the
company1. The production plan is based on the forecasted demand, the available capacity,
and the company’s strategic objectives2. The production plan is also used to authorize and
guide the master schedule, which is a more detailed and short-term plan that specifies the
quantity and timing of each end product to be produced in each time period3. The master
schedule is derived from the production plan, and it must not exceed the production plan’s
limits. Therefore, the major contribution of the production plan is to provide authorization for
the master schedule.
The other options are not correct, because they are either irrelevant or inaccurate. The
production plan does not establish demand by end item, but rather responds to the
forecasted demand by end item. The production plan does not identify key resources to
support the master schedule, but rather determines the overall resource requirements to
meet the production targets. The production plan does not establish the weekly build
schedule, but rather provides the basis for the weekly build schedule, which is a more
detailed breakdown of the master schedule that specifies how many units of each end
product will be built in each week.
References:
Production Planning - Definition, Objectives, Types, Importance
Production Planning in Manufacturing: Best Practices for Production Plans
Master Production Schedule (MPS) - Definition & Examples | Marketing Tutor
[Master Production Schedule (MPS) - Meaning & Process | Tallyfy]
[Production Planning - an overview | ScienceDirect Topics]
[Production Planning: Definition, Levels, Objectives and Factors]
[What Is a Weekly Build Schedule? | Bizfluent]
The most relevant measure of customer service performance is:
A. service perceived by the customer against service expected by the customer.
B. service promised to the customer against service measured by the supplier.
C. customer complaints received as a percentage of orders shipped.
D. positive customer feedback as a percentage of customer feedback.
Explanation: Customer service performance is the degree to which a product or service meets or exceeds customer expectations. The most relevant measure of customer service
performance is how the customer perceives the service compared to what they expected.
This measure reflects the customer’s satisfaction and loyalty, which are key factors for
business success. Other measures, such as service promised versus measured, customer
complaints, or positive feedback, are more related to the supplier’s perspective and may
not capture the customer’s true perception of service quality.
References : CPIM Part 2
Exam Content Manual, Domain 3: Plan and Manage Demand, Section A: Demand
Management, Subsection 4: Customer Service Management, Page 11.
Page 3 out of 13 Pages |
Previous |