A task has an early start of day 4. late start of day 14. early finish of day 10. and a late finish of day 20. What is the task's float?
A. 4
B. 10
C. 20
D. 9
What do you call a person authorized to represent another (the principal) in some capacity? He/she can only act within this capacity or "scope of authority" to bind the principal.
A. Engineer
B. Alternate
C. Project Manager
D. Agent

The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from
the right side of your split screen, using the drop down menu, to reference during your
response/choice of responses.
An unbalanced bid methodology can best be used by:
A. Engineer/contractor working for the owner (Plan B)
B. Subcontractor working for contractor (Plan A or B)
C. Contractor working directly for engineer (plan A or B)
D. Engineer working for the owner (Plan A)
Some of the principles of good communication are:
A. Seek to clarify your ideas before communicating; examine the true purpose of each communication; consider the total physical and human setting whenever you communicate; be mindful, while you communicate, of the overtones as well as the basic content of the message
B. Tell the other person what to do; give insincere praise; psychoanalyze the other person; make light of a serious problem; do not gain the trust of anyone; always have a hidden agenda
C. Use short words; avoid jargon; avoid acronyms and abbreviations; use complete sentences; have a beginning, middle and end; be accurate; be interested in what topic is being communicated
D. The social process by which people in a specific situation construct meaning using symbolic behavior
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of thedesign contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. According to Maslow's hierarchy of needs, giving the employees an award that acknowledges their achievements is most likely to satisfy which level of need?
A. Belonging needs
B. Safety needs
C. Self-actualization
A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%. Is a rise in the price level of a good or service, or market basket of goods and/or services.
A. escalation
B. deflation
C. incremental costs
D. inflation
refers to the process of calculating and reporting the non-monetary functions of the strategic asset portfolio.
A. Asset performance assessment
B. Asset project reporting
C. Asset investment decision and funding
D. Asset performance measurement
A small hole construction project has a baseline budget of $1,000,000. The project is
scheduled to be constructed in 12 months. At the and of the first month, the project data is
reported as below:

The following question requires your selection of Scenario 1.4.162 from the right side of
your split screen, using the drop down menu, to reference during your response/choice of
response. The budgeted cost work performed is;
A. $90,000
B. $100,000
C. $95,000
D. $108,000
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of thedesign contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. Which of the following percent complete measurement techniques is best suited for longterm non-production accounts (such as overhead accounts)?
A. Ratio/level of effort
B. Start/finish
C. Units completed
D. Incremental milestone
A major theme park is expanding the existing facility over a five-year period. The design
phase will be completed one year after the contract is awarded. Major engineering
drawings will be finalized two years after the design contract is awarded and construction
will begin three years after the award of the design contract. New, unique ride technology
will be used and an estimate will need to be developed to identify these costs that have no
historical data.
Resource planning must take all of the following into account except:
A. Types of materials, equipment and labor skills required to complete the project
B. Cash flow (expenditures) limitations for completing work on the project
C. Time available to complete the project
D. Earned value techniques established for the project
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. According to Maslow's hierarchy of needs, which level should be satisfied first?
A. Physiological
B. Self-actualization
C. Safety needs
D. Ego-status

The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from
the right side of your split screen., using the drop down menu, to reference during your
response/choice of responses.
What is the range of unit costs?
A. $21.57
B. $26.65
C. $48.22
D. $485.00
| Page 6 out of 19 Pages |
| 345678 |
| CCP Practice Test Home |
Real-World Scenario Mastery: Our CCP practice exam don't just test definitions. They present you with the same complex, scenario-based problems you'll encounter on the actual exam.
Strategic Weakness Identification: Each practice session reveals exactly where you stand. Discover which domains need more attention, before Certified Cost Professional (CCP) Exam exam day arrives.
Confidence Through Familiarity: There's no substitute for knowing what to expect. When you've worked through our comprehensive CCP practice exam questions pool covering all topics, the real exam feels like just another practice session.